Ambitious Investment Plans for This Year as Well

Recognising the importance of a secure and high-quality electricity supply for customers, and taking into account above all the current condition of the existing electricity distribution network, which affects the quality of supply to customers, CEDIS has allocated more than €30 million through its investment plans for this year. Their implementation will improve the electricity distribution system and enable the required standards to be met in the delivery of electricity.

The allocated funds are around €6 million higher than in the previous year, clearly demonstrating that our company’s plans are becoming increasingly ambitious year after year, and that work on the electricity distribution network is becoming ever more intensive and demanding.

An analysis of the current condition of the electricity distribution system, together with an assessment of implementation risks, determined the priority investment projects for 2025, in both the primary and secondary networks. These projects are expected to deliver a range of positive outcomes: increased capacity to connect new customers, improved voltage conditions, greater supply reliability and security, and reduced electricity losses.

Alongside investments scheduled to begin this year, work is continuing on projects whose preparation and implementation began in the previous period. These include investment activities at six 35/10 kV substations. In the coming period, CEDIS will begin implementing several major investments in the primary network. The most significant include the construction of two 35/10 kV substations, TS “Tivat 3” and “Rijeka Crnojevića”, as well as the construction of 35 kV switchgear at TS 110/35 kV “Buljarica–Kufin”, 10 kV switchgear at TS 110/10 kV “Podgorica 7”, and 10 kV switchgear near the “Rijeka Mušovića” small hydropower plant. In addition to these activities focused on the construction of the aforementioned substations and switchgear, plans include the refurbishment of seven 35/10 kV substations—“Tuzi”, “Unač”, “Ptič”, “Andrijevica”, “Velika Plaža 1”, “Velika Plaža 2” and “Čanj”—as well as the refurbishment of the existing 35 kV switchyard at Buče (installation of 10 kV switchgear and a 35/10 kV transformer), with integration into the 10 kV network, and the 10 kV and 35 kV switchgear at TS 35/10 kV “Rade Končar”. The current year’s plan also includes the procurement of composite conductors and suspension hardware to replace the existing conductors on existing 35 kV overhead lines, at a value of approximately €1.2 million, as well as the procurement and installation of reclosers on 35 kV overhead lines, at a value of approximately €0.2 million.

As the public is already aware, CEDIS will use a €35 million loan from the European Bank for Reconstruction and Development to finance the implementation of the SCADA and ADMS systems project, as well as the procurement of a number of next-generation meters. The introduction of SCADA and ADMS systems is a key step towards modernising the electricity distribution network and will undoubtedly significantly improve the reliability, efficiency and security of the electricity system.

In addition, in early December 2024, the World Bank’s Board of Directors approved financing for the implementation of the Montenegro Energy Sector Decarbonisation Project. The project предусматривает the replacement of seven 35 kV switchgear units at 110/35 kV substations, in facilities acquired from CGES in the previous period, as well as the replacement of 36 old transformers with a 35/10 kV transformation ratio with new, lower-loss units, in accordance with the requirements of the second phase of the Regulation on the Ecodesign of Transformers. The loan agreement between the World Bank and the Ministry of Finance was signed at the end of the previous year, while the conditions for the loan to become effective were met on 14 February 2025.

In addition to the aforementioned primary network facilities, our company is also laying electricity infrastructure as part of the construction works on the Jaz–Tivat boulevard, as well as along the boulevard through Tivat itself. The design documentation has already been prepared, and the value of this CEDIS investment is approximately €5 million.

At the secondary distribution network level, work is planned on 268 projects involving the construction of new 10/0.4 kV substations, the installation of reclosers on 10 kV overhead lines, and the refurbishment of existing 10/0.4 kV substations, which will be fitted with new medium- and low-voltage switchgear and 10/0.4 kV transformers. The total value of these projects exceeds €6 million. Further work on the Medium- and Low-Voltage Network Revitalisation Project will also continue, with €9 million in investment planned for the current year. The project provides for the revitalisation of four 10 kV overhead lines—“Novo Selo”, “Arbaneš”, “Pavino Polje” and “Strahov Do”. Nearly 1,500 poles will be replaced and 52 10/0.4 kV substations revitalised at these electricity facilities.

The installation of new meters and the relocation of metering points will also continue, and the launch of Phase IV of the AMM project is planned, with approximately €12 million to be invested.