The Montenegrin Electricity Distribution System has begun preparatory activities for the introduction of the SCADA system—the most advanced technological solution for network management, analysis and optimisation.
Preparations are currently under way at 35/10 kV substations for the SCADA system. These involve the complete refurbishment of primary equipment and the installation of communications equipment, followed by the provision and establishment of a reliable communications system with associated equipment, and then the preparation and installation of the SCADA system at the Dispatch Centre.
Work to prepare the substations began at the Bioče Substation in Podgorica.
“The SCADA system will be implemented in the first phase at 40 substations with a voltage level of 35/10 kV. Earlier analyses showed that 15 of them are not in a condition to support this advanced system,” said Sreten Krstajić, Head of the 20 kV and 35 kV Maintenance Sector, announcing a second phase that will involve inspections, surveys and preparations at the remaining 80 substations at that voltage level.
According to Krstajić, certain preparatory works were carried out at the Bioče Substation before these activities began, so that the period during which customers are without power would be as short as possible.
– Some parts of the plant are being prepared and assembled in the makeshift workshop of the 20 kV and 35 kV Maintenance Sector. The most significant part of the preparatory work involves wiring and configuring modern digital relay devices, which enable the substation operator to view all the most important system parameters in real time, as well as to operate the switching equipment. At a later stage of the project, this will also be possible from the substation computer. Once the entire project has been completed, all system components will be interconnected in a way that enables remote monitoring and control of all substations from the Dispatch Centre, Krstajić noted.
Sreten Krstajić
Once the Maintenance employees have completed their part of the work, the installation of fibre-optic cables to the control panel will continue. The switching operator will then be able to view the switching status of each cubicle individually on a computer, and, once the project has been implemented, so will the dispatcher at the Dispatch Centre.
Krstajić says that work at all 15 substations, ten of which are on the coast, is scheduled to be completed by the end of the year. After work at the Bioče Substation is completed, activities will shift to the coast so that part of the plan can be completed before the start of the tourist season, when work requiring a power outage is not possible.
We would like to remind you that one of CEDIS’s strategic projects is the implementation of “smart grids” in the electricity distribution system. This involves establishing a SCADA/ADMS system for remote control of distribution substations (110/35 kV, 110/20 kV, 110/10 kV, 35/10 kV) throughout Montenegro, with the project valued at €25 million.
Implementation of the SCADA/ADMS system enables efficient management of the electricity distribution network based on real-time information about network processes. This includes visualisation of network processes and the ability to respond promptly to prevent overloads, thereby reducing the number of interruptions and ensuring a more reliable and higher-quality electricity supply for customers. Full transparency of network activity will also generate significant savings by further reducing losses in the electricity distribution system. In addition, advanced electricity distribution network management systems are essential to the “green transition”, as they provide detailed information and enable efficient management of energy flows from renewable sources.