Users of the electricity distribution system consumed a total of 204,168,919 kWh of electricity in September, approximately 23 percent less than in August.
The largest amount of electricity, or almost 36 percent, was distributed to users in the areas of Podgorica, Danilovgrad and Cetinje (Region 2).
A total of 372,289 metering points were read in the previous month, or 93 percent of the total number (unread metering points are located in properties that are not permanently occupied). The reading rate for metering points equipped with new electronic meters is 99 percent.
In September, the Maintenance Sector teams carried out field interventions 1,563 times. The value of works on the maintenance of electricity infrastructure amounted to approximately 166,000 thousand euros.
During September, construction of three 10/0.4 kV substations, with a value of approximately 131 thousand euros, was completed in Podgorica, Danilovgrad and Tuzi.
In the previous month, activities were also initiated to obtain the necessary documentation for the construction of 14 medium- and low-voltage facilities, with a total value of approximately 688 thousand euros. The necessary documentation is also being obtained for the construction of the 35 kV “Humci–Rijeka Crnojevića” power line, for which approximately 126 thousand euros has been allocated.
316 new users were connected to the distribution network in September.
In the previous month, 1,362 new electronic meters were installed across Montenegro. The total number of metering points in Montenegro equipped with remotely managed electronic meters is approximately 317 thousand, covering around 79 percent of the customer base.
CEDIS’s core activity is the distribution of electricity, and the construction and maintenance of distribution facilities and the network. CEDIS distributes electricity to approximately 400 thousand users across Montenegro.