Title: DECARBONISATION OF MONTENEGRO’S ENERGY SECTOR – COMPONENT 2
Financed by: World Bank
Implemented by: Crnogorski elektrodistributivni sistem d.o.o. Podgorica
Duration: 18 December 2024–30 April 2030
Value: EUR 21.8 million
Description: Component 2, “Increasing the Operational Efficiency of the Electricity Distribution Network”, consists
of the following subcomponents:
| Subcomponent 2.1 – Reconstruction of 35 kV switchgear at 110/35 kV substations |
| Subcomponent 2.2 – Replacement of transformers |
Subcomponent 2.3 – Pilot investment to improve the “visibility” of the low-voltage network |