Danilovgrad: Installation of new 35 kV switchgear completed

Installation and commissioning of a new 35 kV metering cell at the 35/10 kV Danilovgrad substation were completed this month. The value of the contracted works is nearly €72,500 and included the installation of a new metering cell manufactured by Schneider Electric of Germany. With the completion of the project, the Danilovgrad area will have a more reliable and higher-quality electricity supply.
The aim of this investment project is to improve the reliability of the electricity supply to customers in the Municipality of Danilovgrad by replacing worn-out parts of the switchgear with new ones, thereby extending the service life of the equipment at this exceptionally important substation in the distribution system.