€490,000 for maintenance in October

Users of the electricity distribution system took a total of 191,900,832 kWh of electricity in October, around two per cent more than in September and at the same level as in October last year.

The largest amount of electricity, or almost 40 per cent, was distributed to users in the areas of Podgorica, Danilovgrad and Cetinje (Region 2).

From the beginning of the year to the end of October, a total of 2,185,231,476 kWh of electricity was taken, around four per cent more than in the same period last year.

A total of 344,982 metering points were read in the previous month, or 91 per cent of the total number (unread metering points are located in buildings that are not permanently occupied).

The reading rate for metering points equipped with new electronic meters is 99 per cent.

In October, the Maintenance Sector teams carried out 1,809 field interventions. The value of work on maintaining electricity facilities amounted to around €490,000.

Last month, 339 outages were announced across Montenegro due to planned network works. The average duration of the outages was around 2.7 hours. We remind users that planned works are carried out to ensure a higher quality and more reliable electricity supply, and users are informed daily about the work schedules through the media, the website and the Facebook page.

During October, 1,931 new electronic meters were installed in Montenegro. The total number of metering points in Montenegro equipped with remotely managed electronic meters is around 266,000, covering approximately 70 per cent of consumption.

In the previous month, 273 new users were connected to the distribution network.

CEDIS’s core activities are the distribution of electricity and the construction and maintenance of distribution facilities and the network. CEDIS distributes electricity to around 380,000 users across Montenegro.