Extreme temperatures, record consumption and illegal connections placed additional strain on the electricity distribution system in June

The heatwave that affected Montenegro in recent weeks caused record loads on the electricity distribution network for this time of year. In the areas of Podgorica and the coastal municipalities, electricity consumption was recorded at an average of around 30 per cent higher than during the same period last year. Similar challenges are not unique to Montenegro, but are also present in countries across the region and throughout Europe.

The combination of record network loads and extremely high temperatures led to an increase in the number of faults and power outages.

The large number of illegal connections, which pose a particular challenge for the distribution system, undoubtedly contributed to this as well. Years of illegal construction have placed additional strain on CEDIS’s capacity and threatened the quality and security of supply for all users. This is borne out by the fact that, of the total 470,000 users in Montenegro, as many as 90,000 are listed in our database as illegal. Damage to underground power cables caused by investors during construction works also poses a serious problem for the electricity network, as in most cases they do not apply for underground utility records, despite CEDIS having repeatedly warned about this.

During June, several outages were recorded in the Podgorica area, leaving users in the settlements of Zagorič, Kučka Korita and Barutana without electricity for several hours at a time. The same was true for users in the Zeta area.

According to data from the Institute of Hydrometeorology and Seismology, more than 1,000 lightning strikes were recorded across the Balkans in five-minute intervals between 5 p.m. and midnight on 30 June. As a result of these weather conditions, the 10 kV “Ubli”, “Medun” and “Kržanja” overhead lines were left without power, leaving users in the Kuči area without electricity for several hours. Despite the difficult working conditions, CEDIS crews promptly went out into the field to repair the fault as quickly as possible.

During the same period, lightning strikes also left part of the Zeta and Barutana load area without power. Our crews located the fault on the 35 kV “Gornja Zeta – Golubovci” overhead line and repaired it as soon as conditions allowed for safe work.

The Kuči area was also hit by severe storms between 22 and 25 June. Heavy rainfall, hail, strong wind gusts and intense lightning strikes caused a fault on the 10 kV “Ubli” overhead line. Despite the difficult working conditions, CEDIS on-call crews worked continuously on this line to restore the electricity supply as quickly as possible.

With regard to the “Ubli” overhead line, which is 18.2 kilometres long, it is important to note that the company is nearing completion of its reconstruction. To date, 169 of the 184 poles have been replaced, more than 10 kilometres of new conductor have been installed along with the associated equipment and insulators, and 11 of the 14 10/0.4 kV transformer stations have been refurbished. More than €300,000 has been allocated for this work. Planned outages are also necessary during these works. The fault in question occurred on the section of the overhead line that has not yet been reconstructed, and the work is scheduled to be completed by the end of summer. In this area, 190 illegal and 141 legal users have also been recorded, placing additional strain on the system and affecting the reliability of supply.

Since 29 June, outages have also been recorded at the 10/0.4 kV transformer stations “Zagorič 2”, “Zlatica 3” and “Kapela Zagorič”, caused by transformers overheating as a result of overloading and extreme heat. Users in part of Zagorič Forest Park, the area around the cemetery in Zagorič and part of Nikole Tesle Street were left without power. The extent of the load on this part of the network is best illustrated by the fact that there are 133 illegal users in the area, which significantly increases the network load, particularly during periods of record consumption.

Damage to the 10 kV “Zlatica” cable caused by contractors carrying out road reconstruction works near the cemetery in Zagorič further disrupted the electricity supply. As a result, the MBTS “Stara Zlatica”, STS “Stara Zlatica” and BTS “Stara Zlatica” transformer stations were left without power from 16 to 22 June. There is also a large number of illegal users in this area.

Between 22 and 23 June, part of Podgorica was also left without power due to faults on the 35 kV cable circuits along the “Podgorica 1 – Gorica A” section (KB Gorica 1 and KB Gorica 2). These cables have been subject to numerous relocations and interventions in recent years as a result of intensive construction and the development of municipal infrastructure. Such works can cause mechanical stress and degradation of the cable insulation system, which over time reduces reliability and increases the likelihood of faults, particularly during periods of increased load on the electricity distribution network.

During the same period, the significantly increased load on the electricity distribution network also caused an outage on the 35 kV “Podgorica 1 – Gornja Zeta” overhead line. This was due to the operation of the relay protection system, which detected conditions that could have threatened the security of the electricity system—specifically, a fire at a cable termination. As a result, users in the Zeta area were temporarily left without electricity. CEDIS responded quickly, repaired the fault and restored the regular electricity supply to users.

We must also point out that restoring the network to its normal switching configuration no longer depends solely on CEDIS in some cases. An increasing number of electricity facilities in the distribution system are owned by third parties. Although CEDIS operates the distribution system, switching operations at facilities owned by other legal entities do not fall within its remit. Consequently, after certain outages, it is necessary to wait for employees of those companies to arrive so that the facilities can be brought back into operation and the electricity supply to users restored.

CEDIS therefore faces the consequences of increased system loads every day, even though the causes are not always directly within its remit. Addressing illegal construction and illegal connections requires coordinated action by all relevant institutions.

We remind the public that CEDIS invested more than €35 million in network development and modernisation last year, of which almost €12 million was allocated to the secondary network (10 kV and 0.4 kV), while more than €7 million was invested in increasing system capacity and reliability. Investing millions in the system to provide users with the highest possible quality and reliability of supply is a priority for CEDIS, but the challenges described above mean that faults and outages cannot be avoided.

Finally, we urge citizens to use electricity responsibly during periods of extremely high temperatures in order to reduce the load on the system and prevent situations like these. We also urge investors and contractors to obtain information on underground utilities as required and to comply with the prescribed procedures, in order to prevent damage to electricity infrastructure and outages lasting several hours.