CALL FOR PROJECTS “ENERGY UNDERLINED IN GREEN”

The Montenegrin Electricity Distribution System, in cooperation with the Institute for Education of Montenegro, which implements the international “Eco-Schools” programme, announces a CALL FOR PROJECTS “ENERGY UNDERLINED IN GREEN” in the field of environmental protection. ELIGIBILITY Educational institutions implementing the international “Eco-Schools” programme are eligible to participate in the call, specifically those holding the international

IN MEMORIAM

Sanja Tomić 1974 – 2026 Head of the Investment Sector We mourn the passing of our colleague Sanja Tomić, Head of the Investment Sector. Her kindness, professionalism and dedication to the company, as well as to every task entrusted to her, will remain in our lasting memory. Her selfless collegiality will be missed by everyone

Substation “Bigova” to Be Energized in September; TS “Tri Krsta” Ready on Luštica

The Montenegrin Electricity Distribution System has successfully completed construction of the new 35/10 kV “Bigova” substation, including its integration into the 35 kV and 10 kV networks. This major investment, worth close to €2.9 million, is expected to be commissioned in September. Its commissioning will significantly improve the reliability and quality of supply for consumers

CEDIS Registered as a Provider of Electronic Communications Infrastructure Lease Services

The Montenegrin Electricity Distribution System has successfully completed the registration process in the Register of Electronic Communications Operators maintained by the Agency for Electronic Communications and Postal Services. With this step, our company officially acquired the status of a provider of electronic communications infrastructure lease services on 13 August. The acquisition of this status is

CEDIS Puts 100 Gbps Connection Between Podgorica and Mojkovac into Operation

As part of the continued enhancement of CEDIS’s business information network, a 100 Gbps connection has been put into operation between the administrative building in Podgorica, where the Data Centre is located, and the office building in Mojkovac, where a backup Data Centre is being established. The new connection is a key communications prerequisite for

Bojan Nikitović appointed Chairman of the Board of Directors, Vladimir Čađenović appointed CEO of CEDIS

At the 25th regular General Meeting of CEDIS LLC Podgorica, held today, new members of the Board of Directors of the Montenegrin Electricity Distribution System were appointed in accordance with the Law on Business Companies and the CEDIS Statute. The new Board of Directors comprises: At the first constitutive meeting of the Board of Directors

CEDIS INVESTS EUR 1.5 MILLION IN ITS OWN FIBRE-OPTIC INFRASTRUCTURE

Over the past three years, CEDIS has invested a total of EUR 1.5 million in activating its own fibre-optic infrastructure, which enables fast, reliable and secure data transmission, enhances the protection of information systems and creates the conditions for more efficient management of the distribution network. The investment covers the development of an active fibre-optic

CEDIS Marks a Decade of Successful Operations: Awards for Top Employees and Donation to the Protection and Rescue Service

Crnogorski elektrodistributivni sistem (CEDIS) marked ten years of independent operations by presenting awards to employees who, through their work, professionalism and dedication, have made a special contribution to the company’s development. At CEDIS’s Administration Building, awards were presented to individuals who exemplify responsibility, expertise and team spirit. At the reception, Vladimir Ivanović, CEDIS Executive Director,

Extreme temperatures, record consumption and illegal connections placed additional strain on the electricity distribution system in June

The heatwave that affected Montenegro in recent weeks caused record loads on the electricity distribution network for this time of year. In the areas of Podgorica and the coastal municipalities, electricity consumption was recorded at an average of around 30 per cent higher than during the same period last year. Similar challenges are not unique